ABOUT

El Paso County is undertaking an update of the standards that guide engineering and development across the county. The Engineering Criteria Manual (ECM) and Drainage Criteria Manual (DCM) updates are being coordinated by County staff from the Department of Public Works and Engineering Division, with guidance from an Stakeholder Group of local community agencies and development professionals, with technical expertise provided by IMEG Corp., a nationally recognized engineering and consulting firm.

Phase 1


Project Kick-Off

August 2025

Phase 2

Standards Assessment

August - October 2025

Project Timeline

Phase 3

Standards Drafting

October 2025 - August 2026

Phase 4

50% Progress Set & Stakeholder Review

September 2026

Phase 5

75% Progress Set & Stakeholder Review

February 2027

Phase 6

90% Progress Set

April 2027

Phase 7

Completion & Adoption of ECM

June 2027

The project timeline includes seven phases: Phase 1: Project Kick-Off begins in August 2025. Phase 2: Standards Assessment runs from August through October 2025, followed by Phase 3: Standards Drafting from October 2025 into August 2026. Phase 4: 50% Progress Set and Stakeholder Review occurs in September 2026, and Phase 5: 75% Progress Set and Stakeholder Review in February 2027. Phase 6: 90% Progress Set occurs in April 2027. The project concludes with Phase 7: Completion and Adoption of the ECM in June 2027.